Hunter Valley, NSW

  • Project Value$20M
  • Year of Completion2012

Coal Handling Processing Plant

Supply of 28 x Switchrooms fully integrated with Motor Control Centers, VVVF Drives, UPS, Communications, PLC Panels fully integrated including the supply of 700 x Field Panels.